Gunnebo Speedstile Fl Installation Manual

The installation typically involves securing the cabinets using anchor bolts, requiring a minimum bolting depth of 70mm into concrete. Installation Procedure Gunnebo SpeedStile FLS Installation Guide

The SpeedStile will perform a self-test routine. The wings will cycle open and closed to find their mechanical limits. Sensor Calibration Access the main control board menu.

Run separate underground conduits for high-voltage power cables and low-voltage signal/network cables. gunnebo speedstile fl installation manual

: Position units to be perfectly parallel. The Master unit should ideally be on the secure (exit) side of the lane. 3. Mechanical Installation

Check the alignment of the infrared photocell beams along the inside of the cabinets. Clean the lenses with a microfiber cloth. If a beam is misaligned, the control board will trigger a continuous fault code. Safety Testing: Sensor Calibration Access the main control board menu

Prepare the floor cabling, ensuring access to a reliable power source and network cabling for access control integration.

: Passage in one or both directions is electronically controlled. The flap leaves open only upon receiving a valid signal from the access control system or remote release. This mode provides the highest security level. The Master unit should ideally be on the

: The floor must be level within +/- 5mm over the entire footprint of the SpeedStile unit.

Handle the Gunnebo SpeedStile FL components with extreme care, particularly the glass panels and polished stainless steel cabinets. Main Components

Cables must rise from the foundation into the designated shaded areas within the cabinet base. Conduit Depth : Conduits should run at least 140mm below finished floor level. Conduit Rise : Conduits must rise at least 50mm from the foundation to prevent water ingress. Conduit Diameter : Use a minimum diameter of Power Supply : Standard operation requires 230Vac / 50Hz (115Vac available as an option). Power rating is roughly 120VA on standby 300VA during operation Fichet Security Solution 3. Installation Steps Gunnebo SpeedStile FLS Installation Guide | PDF - Scribd

Place the cabinets over the pre-drilled cable conduits.

Gunnebo Speedstile Fl Installation Manual

17662 Irvine Blvd #14
Tustin, CA 92780

Gunnebo Speedstile Fl Installation Manual

SUPPORT@RXCITY.COM

PHONE: + 1 (949) 298-6600

COPYRIGHT © 2023 | DIGITAL BUSINESS SOLUTIONS, INC. | ALL RIGHTS RESERVED
Digital Business Solutions, Inc. is a registered Independent Sales Organization of Wells Fargo Bank, N.A., Concord, CA