Perform a dry run of the boom through the planned path of travel to ensure structural clearances. Step 5.2: Electrical De-energization (Partial)
The crane is rotated to the pre-agreed "parked" position to allow the assist crane access.
All lifting accessories (slings, shackles, chains) must possess valid thorough examination certificates (e.g., LOLER/OSHA logs) and color-coded tags.
Any ballast weights at the base are loaded onto transport trucks. 6. Safety & Environmental Controls tower crane dismantling method statement
Controls the immediate dismantling zone and coordinates the team.
Establish a strict exclusion zone beneath the entire swing radius of both the tower crane and the mobile crane. Use solid barriers and signage reading: "DANGER: OVERHEAD LIFTING IN PROGRESS – KEEP OUT."
Below is a comprehensive, standard engineering method statement template designed for high-rise and commercial construction projects. 1. Project Overview & Scope of Work 1.1 Objective Perform a dry run of the boom through
Operations must be postponed in cases of heavy rain, lightning, dense fog, or poor visibility. Working at Height
All lifting gear (slings, shackles, chains) must have valid test certificates. 3. Personnel & Responsibilities
Finalize all "Lift Plans" and obtain local authority approvals for mobile crane placement. 2. Equipment Requirements Assist Crane: Any ballast weights at the base are loaded
All dismantling activities must strictly adhere to the latest editions of the following standards and documentation:
A comprehensive method statement should include or reference: